Tibet Infrastructure: Nyingchi Railway Station to be Completed in October 2021

Published Jan 05, 2020
Updated Mar 26, 2020

According to Tibet News Network report on 31 December 2019, the construction of Nyingchi (Linzhi) Railway Station in Tibet Autonomous Region, China is expected to be completed in October 2021. Nyingchi Railway Station is located in Zire Village, Bujiu Township, Bayi District, about 19 kilometers from Bayi Town in Nyingchi City, and 30 kilometres from the Milin(Mainling) Airport of Nyinghchi (Linchi). 

The designed building area of Nyingchi (Linzhi) Railway Station building is 15000 square meters. It has two floors above ground and a part of the underground one is for passenger passages, fire pump house and pools. The main body is a reinforced concrete frame structure and the roof of the station hall is a steel and wooden frames structure.

According to Wang Zhuopei, deputy director of the Department of Safety and Quality of Tibet Railway Construction Co. Ltd, as of the end of December 2019, the main railway bed project of the Lhasa-Linzhi Railway has been completed, and the left over are the works attached to the land base and greening projects. 84.7 kilometres of bridge project has been completed which is 98.22% of the total designed bridge project. Construction of 44 tunnels of 213.48 kilometres has been completed, which is 98.62% of total designed tunnel projects, the remaining 3 tunnels have not yet linked up. Building construction projects in over 14400 square meters area have been completed which is 64.43% of total designed building projects. 77500 square meters area building projects are remaining.

In 2020 will Speed up the Start of Construction of Lhasa-Rikaze Expressway

The “Thirteenth Five-Year Plan” is coming to an end. In 2020, the Autonomous Region Transportation Department will continue to take “Not to seek a pretext, not to push responsibilities, not to bargain over terms, dare to take responsibilities and plan ahead” as the working guidelines. It will focus on the areas of ‘arrange the plans reasonably and actively implement the investment’. It will strengthen the docking efforts and ensure project construction, further increase the reporting and docking efforts to relevant national ministries and commissions, advance the preliminary work, and ensure project reserves.

Make plans scientifically and strive to achieve the goals. Based on the progress of the “13th Five-Year Plan” projects, rationally formulate the annual road transportation fixed asset investment plans, clarify mission objectives, and accelerate project construction. At the same time will strengthen the communication, connection and reporting with relevant national ministries and commissions to lay the foundation for the start of the 14th Five-Year Plan.

Strengthen overall coordination and advance planning work. Strive to review and approve the “Tibetan Autonomous Region Comprehensive Three-Dimensional Transportation Network Plan (2021-2050)” in the first half of the year. According to the report on the docking with the national ministries and commissions, it will revise and improve the “Fourteenth Five-Year Plan for the Development of Comprehensive Transportation in the Autonomous Region” and submit it to the Autonomous Region Government for approval.

The second round of environmental inspections is about to begin, and we are well prepared for the second round of environmental inspections. Firmly establish the concept of ecological civilization that respects nature, conforms to nature, and protects nature; practically enhance the sense of responsibility and responsibility for protecting the ecological environment, strictly implement the environmental protection responsibility system of “one position, two responsibilities”, and insist on the work principle that “managing the industry must manage environmental protection, managing the professional work must manage the environmental protection and managing the production must manage environmental protection, manage production and operation must manage environmental protection; to earnestly perform environmental protection functions and responsibilities, work together to protect various environmental protection tasks, and strive to form a good situation of collective management.

“In the construction of key transportation projects in 2020, we must first strive to complete the construction of the main project of the Lhasa to Nagqu(Naqu) Expressway and strive to reach the traffic conditions. Second, to accelerate the construction of the Lhasa to Shigatse Expressway, which are conditions created to realise in the beginning of the 14th Five-Year Plan. In addition, the controlled project from Medog to Chayu is also planned to start construction this year”, Li Dongchang said.